1.Installation of the rack: Install the rack according to the size and requirements of the installation drawing. After installing all the racks, adjust each leg until the machine is combined with the requirements. The head and tail should be adjusted in time when the dislocation is too large. After the adjustment, the head must be firmly fixed on the platform, and the tail should be fixed on the embedded foundation bolts to prevent the conveyor from shaking and displacement during operation.

2.To clean the conveyor belt and belt pulley, we should use the rag to dip volatile liquid to wipe conveyor belt, soaking in detergent or using detergent to scrub the conveyor belt is not advisable; In order to remove grease and dirt, it is obviously not advisable to rub with sandpaper or scrape with a sharp object. Conveyor belt must be kept dry before installation and use.

3, The installation of the belt: when installing the belt, we should pay attention to measuring the contact size of the belt, ensure that the belt and the track fully contact, avoid distortion or deviation, measure the accurate length and then ring butt

4, The tension adjustment of belt conveyor: belt conveyor tension is normal or not directly affects the use of the effect and service life of the conveyor. Belt conveyor tension is too loose will cause the conveyor belt deviation, too tight and affect the service life of the belt, even can not rotate or rotate the belt jumping up and down. Commissioning and installation of belt conveyor should first adjust the parallelism and levelness of the belt, parallel is not good enough to form the uneven force of the belt, the levelness is less than the belt deviation. The initial adjustment of belt tension should be a little looser than normal tension, but not too loose.

5. Before the empty car test run, it is necessary to check whether there are tools, iron parts or other sundries left on the conveyor, and if there are, it should be removed; And for all bearings, tail bearing seat guide rail, give enough lubrication; Check all parts of the conveyor

6, Connect the power supply, point drive several times, such as normal operation, can make the conveyor continuous operation.
7, We should be responsible for observing the operation of the situation, such as head, tail and the middle of the main parts.  
8, when the empty car test run for half an hour and the operation is normal, can gradually add material, load test run, can not be loaded before starting, when parking the material in the conveyor to be discharged after all can stop.


The above is the installation and debugging of the belt conveyor. If you want to know more about the equipment, like trommel screen,  crushing machine, shaftless trommel screen, ball mill, furnace, briquette machine, trommel filter, etc,. Please consult the customer service staff of Zhengzhou Sinolion  Machinery. Zhengzhou Sinolion Machinery is a professional mining Machinery and equipment manufacturer, with rich technical accumulation and project experience, we sincerely invite you to visit our factory!